TIMELINES OF DESIGN APPROVALS AND ELECTRICAL INSTALLATION CERTIFICATE FOR ELECTRICAL INSTALLATIONS AND GENERATORS
Design Approval
1. |
Pre Scrutiny of Design Approval within 3 working days from date of submission of Approval for Electrical Design. |
2. |
Approval of Design will be completed within 11 working days from date of completion of pre scrutiny.
|
Installation Certificate
1. |
Pre Scrutiny of Application submitted towards Electrical Installation Certificate within 1 working day from date of submission of Application |
2. |
Inspection of the Installation will be conducted by the officer within 3 working days from date of completion of pre scrutiny. |
3. |
Form of Order will be issued within 1 working day of after inspection. |
4. |
Electrical Installation Certificate will be issued within 1 working day after submission of satisfactory compliance Report. |