TIMELINES OF DESIGN APPROVALS AND ELECTRICAL INSTALLATION CERTIFICATE FOR ELECTRICAL INSTALLATIONS AND GENERATORS


Design Approval

1. Pre Scrutiny of Design Approval within 3 working days from date of submission of Approval for Electrical Design.
2. Approval of Design will be completed within 11 working days from date of completion of pre scrutiny.

Installation Certificate

1. Pre Scrutiny of Application submitted towards Electrical Installation Certificate within 1 working day from date of submission of Application
2. Inspection of the Installation will be conducted by the officer within 3 working days from date of completion of pre scrutiny.
3. Form of Order will be issued within 1 working day of after inspection.
4. Electrical Installation Certificate will be issued within 1 working day after submission of satisfactory compliance Report.